UPDATE-Secondary Spill At Repair Site
Pumping operations have resumed after a streambank collapsed early Thursday morning at the repair site of a 36” wastewater main.
Pumping operations have resumed after a streambank collapsed early Thursday morning at the repair site of a 36” wastewater main.
Charlotte Water is actively repairing a 36” wastewater main
Charlotte Water (CLTWater) crews responded to a broken wastewater pipe east of E. Mallard Creek Church Road, downstream of Kirk Farm Field Park on October 24th.
The Sugar Creek Wastewater Treatment Plant (near Fairview and Park road intersection) experienced an electrical outage in the afternoon of Tuesday October 17, 2017, and for approximately 12 minutes discharged highly treated wastewater to Little Sugar Creek that had not completed the normal treatment process.