Construction Update: Stewart Creek Greenway Closure – Update #6

CLTWater is meeting with Mecklenburg County in late July to review final asphalt paving and other restoration tasks.

The greenway is estimated to reopen mid-August 2020. We appreciate your patience and understanding during this large wastewater pipe repair.

Detailed updates May through July 2020:

  • The area adjacent to Tuckaseegee Rd. bridge is now fully restored
  • The stone access road was removed, and the entire area was seeded/strawed
  • Rip rap placed along channel which feeds the main creek was installed
  • Crews removed large spoil piles of dirt, grading/drainage, road removal, seed/straw, tree/shrub planting, fence removal, and trail restoration
  • Grass is coming in nicely throughout the park; shoulders along upper greenway trail have been restored with the exception of parking/turnout area
  • Repair site was hydro-seeded and plantings were installed.
  • The lower section of the greenway that was removed is being rebuilt
  • Crews are continuing restoration and preparing area for reopening

Discover more from Charlotte Water Blog

Subscribe now to keep reading and get access to the full archive.

Continue reading

document.addEventListener('DOMContentLoaded', function () { const observer = new MutationObserver(() => { document.querySelectorAll('.jetpack-instant-search__search-result-expanded__image').forEach(img => { if (!img.hasAttribute('alt')) { img.setAttribute('alt', ''); } }); }); observer.observe(document.body, { childList: true, subtree: true }); });