May 14 Update: Long Creek Wastewater Spill
After more than two weeks of construction site preparation and stabilizing bypass operations, Charlotte Water is replacing 140 feet of broken wastewater pipe north of 4100 Oakdale Road. Pipe replacement…
After more than two weeks of construction site preparation and stabilizing bypass operations, Charlotte Water is replacing 140 feet of broken wastewater pipe north of 4100 Oakdale Road. Pipe replacement…
Long Creek Wastewater Spill remediation: Bypass Operations Last Wednesday, contractors set up large bypass lines and pumps to capture wastewater from the end of the broken pipe and pump it…
Wednesday Update: Long Creek Wastewater Spill remediation: Bypass Operations Battling additional storms and adverse weather, crews worked through the night Tuesday to set up bypass pumping operations around the break.…
April 24, 2018 – Charlotte Water (CLTWater) crews responded to a broken wastewater pipe near Oakdale Road on April 23rd. Crews estimate approximately 15.4 million gallons reached Long Creek, part…